Buildings and Facilities17DF0149

COMPLETION OF 4STY 12CL SCHOOL BUILDING AT BAYANAN ES; 4STY 16CL AND 3STY 6CL SCHOOL BUILDING AT BACOOR ES; 4STY 8CL SCHOOL BUILDING AT POBLACION ES (BACOOR ANNEX); 4STY 16CL SCHOOL BUILDING AT HABAY ES; 4STY 20CL SCHOOL BUILDINGAT QUEENSROW ES; AND 4ST

COMPLETION OF 4STY 12CL SCHOOL BUILDING AT BAYANAN ES; 4STY 16CL AND 3STY 6CL SCHOOL BUILDING AT BACOOR ES; 4STY 8CL SCHOOL BUILDING AT POBLACION ES (BACOOR ANNEX); 4STY 16CL SCHOOL BUILDING AT HABAY ES; 4STY 20CL SCHOOL BUILDINGAT QUEENSROW ES; AND 4ST is a DPWH-tracked public work in Cavite 1st DEO, Region IV-A. Reported contract value: ₱38,314,891.45. Status: Reported complete (DPWH). Contractor on record: SELPHAR CONST. Figures trace to dpwh.

Cavite 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱12,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures and other improvements, including removal of informal settlers along Zapote River Barangay Molino 7, Bacoor City, Cavite
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-17-0009159

₱86,116.00 · FY2017

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

30 projects · ₱1.2B total · 0 flags

Other projects by this contractor

CONSTRUCTION OF REVETMENT ALONG CARMONA RIVER (EAST AND WEST SIDE) AT BRGY. LANTIC, CARMONA, CAVITE

Cavite 3rd DEO, Region IV-A

2023₱99.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRA.PROGRAM (BIP) - BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BLDGS/FACILITIES-CONST. OF FLOOD CONTROL STRUCTURES ALONG MAASIM RIVER,BRGY. UPIG, SAN ILDEFONSO, BULACAN (UPSTREAM)

Bulacan 3rd DEO, Region III

2025₱97.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAMCONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERSCONST OF REVETMENT ALONG IMUS RIVER,SEGMENT 2

Cavite 1st DEO, Region IV-A

2024₱95.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BULO RIVER, SAN MIGUEL,BULACAN

Region III, Region III

2023₱95.0M
Reported complete (DPWH)
No sat.

FLOOD CONTROL MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BULO RIVER, SAN MIGUEL, BULACAN

Region III, Region III

2023₱95.0M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCRUES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BULO RIVER, SAN MIGUEL, BULACAN

Region III, Region III

2023₱95.0M
Reported complete (100% progress, DPWH status On-Going)
View all 30 projects →

4. Implementation

Contract Amount

₱38,314,891.45

Progress

Reported complete (DPWH)

Start Date

December 12, 2017

Target End

March 26, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.