Roads23IE0067

ASSET PRESERVATION REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE SECONDARY ROADS, CALUBIAN JCT. SN ISIDRO TABANGO VILLABA PALOMPON RD - K1010+156 K1010+176, K1010+300 K1010+339, K1010+391 K1010+430, K1014

ASSET PRESERVATION REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE SECONDARY ROADS, CALUBIAN JCT. SN ISIDRO TABANGO VILLABA PALOMPON RD - K1010+156 K1010+176, K1010+300 K1010+339, K1010+391 K1010+430, K1014 is a DPWH-tracked public work in Leyte 3rd DEO, Region VIII. Reported contract value: ₱48,509,990.02. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: RJIR ENT CORP. Figures trace to dpwh.

Leyte 3rd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Phase 2, Barangay Sambulawan, Leyte, Leyte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Leyte 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

692 projects · ₱17.7B total · 35 flags

Other projects by this contractor

View all 692 projects →

4. Implementation

Contract Amount

₱48,509,990.02

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

June 21, 2023

Target End

April 20, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.