Flood Control and Drainage25D00256

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGOS RIVER, PACKAGE Z, GENERAL NAKAR, QUEZON

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGOS RIVER, PACKAGE Z, GENERAL NAKAR, QUEZON is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱93,602,652.16. Status: Past target date (DPWH On-Going). Contractor on record: WAYCON BUILDERS AND CONST SUPPLY CORP FOR:WAYCON BUILDERS. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

474 projects · ₱22.2B total · 0 flags

4. Implementation

Contract Amount

₱93,602,652.16

Progress

Past target date (DPWH On-Going)

Start Date

June 9, 2025

Target End

February 3, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.