Construction of Flood Mitigation Structure24KB0180

Construction of Reinforced Concrete Box Culvert, Barangay Sanipon, Kibawe, Bukidnon

Construction of Reinforced Concrete Box Culvert, Barangay Sanipon, Kibawe, Bukidnon is a DPWH-tracked public work in KIBAWE (BUKIDNON), BUKIDNON, Region X. Reported contract value: ₱4,950,000.00. Status: Reported complete (DPWH). Contractor on record: ROJAYME CONST SERVICES. Figures trace to sumbong.

KIBAWE (BUKIDNON), BUKIDNON, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Sinanglanan, Malaybalay City, Bukidnon
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROX-24-0008933

₱1,845,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROX-24-0008934

₱170,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,950,000.00

Progress

Reported complete (DPWH)

Start Date

June 10, 2024

Target End

October 22, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.