Buildings and Facilities24AA0301

IMPROVEMENT OF MULTI-PURPOSE BUILDING, DEPARTMENT OF EDUCATION (DEPED-SDOIN, LAOAG CITY, ILOCOS NORTE

IMPROVEMENT OF MULTI-PURPOSE BUILDING, DEPARTMENT OF EDUCATION (DEPED-SDOIN, LAOAG CITY, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱2,969,812.99. Status: Reported complete (DPWH). Contractor on record: BJMJB CONST. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Darayday Flood Control, Laoag City, Ilocos Norte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Ilocos Norte 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

360 projects · ₱4.5B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD MITIGATING STRUCTURE RIGHT BANK, BARANGAY ISIC-ISIC, VINTAR ILOCOS NORTE (PHASE 2)

Ilocos Norte 1st DEO, Region I

2024₱57.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATIONSTRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OFFLOOD CONTROL STRUCTURE ALONG PADSAN RIVER, BARANGAY10, SARRAT, ILOCOS NORTE (PHASE 2)

Ilocos Norte 1st DEO, Region I

2024₱57.9M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BISLAK RIVER, SITIO DALIM, BARANGAY CABAYO, VINTAR, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2025₱56.4M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BISLAK RIVER, SANJERA BENGBENGKAG, BARANGAY ISIC-ISIC, VINTAR, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2025₱56.1M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DAURAO CREEK, BARANGAY CAAOACAN, LAOAG CITY, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2025₱55.6M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE MANGATO BRIDGE UPSTREAM, LAOAG CITY, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2025₱55.6M
Past target date (DPWH On-Going)
View all 360 projects →

4. Implementation

Contract Amount

₱2,969,812.99

Progress

Reported complete (DPWH)

Start Date

February 21, 2024

Target End

April 20, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.