Roads16BJ0048

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) (INTERMITTENT SECTIONS) ARITAO-QUIRINO ROAD K0272+480-K0272+561.20,K0272+574-K0272+642, K0274+126-K0274+177, ...

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) (INTERMITTENT SECTIONS) ARITAO-QUIRINO ROAD K0272+480-K0272+561.20,K0272+574-K0272+642, K0274+126-K0274+177, ... is a DPWH-tracked public work in Nueva Vizcaya 2nd DEO, Region II. Reported contract value: ₱21,601,795.12. Status: Reported complete (DPWH). Contractor on record: BENSON BUILDERS. Figures trace to dpwh.

Nueva Vizcaya 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Lamo Flood Control Project along Apian River, protecting DM Jct. Lamo - Malasim Road, Lamo Section, Dupax del Norte, Nueva Vizcaya
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-16-0037974

₱485,000.00 · FY2016

Released to Digos City National High School (Davao del Sur (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

18 projects · ₱146.9M total · 0 flags

4. Implementation

Contract Amount

₱21,601,795.12

Progress

Reported complete (DPWH)

Start Date

February 2, 2016

Target End

July 30, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.