Flood Control and Drainage18CK0096

REHABILITATION/IMPROVEMENT OF EXISTING DIKE ALONG RIO CHICO RIVER (LA PURISIMA SECTION, RIGHT BANK) STA. 8+617.60 TO STA. 8+768.00 AT LAPAZ, TARLAC

REHABILITATION/IMPROVEMENT OF EXISTING DIKE ALONG RIO CHICO RIVER (LA PURISIMA SECTION, RIGHT BANK) STA. 8+617.60 TO STA. 8+768.00 AT LAPAZ, TARLAC is a DPWH-tracked public work in Tarlac 2nd DEO, Region III. Reported contract value: ₱23,271,270.71. Status: Reported complete (DPWH). Contractor on record: BIG BERTHA CONST & DEVELOPMENT. Figures trace to dpwh.

Tarlac 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Existing Dike along Rio Chico River, (La Purisima Section, Right Bank), La Paz, Tarlac
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0029562

₱0.00 · FY2018

Released to Division of Tarlac (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

76 projects · ₱4.2B total · 2 flags

4. Implementation

Contract Amount

₱23,271,270.71

Progress

Reported complete (DPWH)

Start Date

April 6, 2018

Target End

September 2, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.