GAA 2025 SSP25BH0183

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, JONES WEST CENTRAL SCHOOL CAMPUS 1, BARANGAY 1, JONES, ISABELA

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, JONES WEST CENTRAL SCHOOL CAMPUS 1, BARANGAY 1, JONES, ISABELA is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱4,801,352.10. Status: Past target date (DPWH On-Going). Contractor on record: CASAN CONST AND TRADING. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (Section 3), Barangay Santa Isabel, Jones, Isabela
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Isabela 4th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

85 projects · ₱626.4M total · 2 flags

4. Implementation

Contract Amount

₱4,801,352.10

Progress

Past target date (DPWH On-Going)

Start Date

August 6, 2025

Target End

January 28, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.