Buildings and Facilities17DH0114

CONSTRUCTION OF FOUR (4) STOREY, TWENTY (20) CLASSROOM SCHOOL BUILDING, STA. MARIA NHS, STA. MARIA, LAGUNA

CONSTRUCTION OF FOUR (4) STOREY, TWENTY (20) CLASSROOM SCHOOL BUILDING, STA. MARIA NHS, STA. MARIA, LAGUNA is a DPWH-tracked public work in Laguna 1st DEO, Region IV-A. Reported contract value: ₱40,322,896.25. Status: Reported complete (DPWH). Contractor on record: MICLOVER GEN CONST. Figures trace to dpwh.

Laguna 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (Upstream and Downstream) of Alumbrado Bridge, Nagcarlan, Laguna
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-17-0013804

₱130,490.00 · FY2017

Released to Tarangnan National Sa High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱40,322,896.25

Progress

Reported complete (DPWH)

Start Date

December 16, 2017

Target End

September 26, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.