Buildings and Facilities17JF0085

CONSTRUCTION OF ONE (1) STOREY TWO (2) CLASSROOM AT MONCHING NHS, SIAY, ZAMBOANGA SIBUGAY

CONSTRUCTION OF ONE (1) STOREY TWO (2) CLASSROOM AT MONCHING NHS, SIAY, ZAMBOANGA SIBUGAY is a DPWH-tracked public work in Zamboanga Sibugay 2nd DEO, Region IX. Reported contract value: ₱2,738,644.66. Status: Reported complete (DPWH). Contractor on record: BARILLO CONST AND ENT. Figures trace to dpwh.

Zamboanga Sibugay 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

140 projects · ₱2.5B total · 0 flags

Other projects by this contractor

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION/IMPROVEMENT OF FLOOD CONTROL FOR PREVENTION AND MITIGATION ALONG BRGY. SAN JOSE-POBLACION IMELDA, PART OF SIBUGUEY RIVER, IMELDA, Z

Region IX, Region IX

2019₱112.1M
Reported complete (DPWH)

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL ALONG KABASALAN RIVER (PHASE III), FL PENA, KABASALAN, ZAMBOANGA SIBUGAY

Region IX, Region IX

2021₱105.1M
Reported complete (DPWH)

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER (PHASE IV), FL PENA, KABASALAN, ZAMBOANGA SIBUGAY

Region IX, Region IX

2022₱104.9M
Reported complete (100% progress, DPWH status On-Going)

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVERS BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER (PHASE V), DOWNSTREAM, CANACAN, KABASALAN, ZAMBOANGA SIBUGAY, PACKAGE 1

Region IX, Region IX

2023₱104.8M
Reported complete (100% progress, DPWH status On-Going)

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVERS BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER (PHASE V), DOWNSTREAM, CANACAN, KABASALAN, ZAMBOANGA SIBUGAY, PACKAGE 2

Region IX, Region IX

2023₱100.0M
Reported complete (100% progress, DPWH status On-Going)

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVERS BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER (PHASE V), FL PENA, KABASALAN, ZAMBOANGA SIBUGAY, PACKAGE 1

Region IX, Region IX

2023₱100.0M
Reported complete (100% progress, DPWH status On-Going)
View all 140 projects →

4. Implementation

Contract Amount

₱2,738,644.66

Progress

Reported complete (DPWH)

Start Date

January 25, 2018

Target End

April 19, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.