Flood Control and Drainage18IC0029

CONST. OF FLOOD CONTROL ALONG SAMBULAWAN RIVER, BRGY. GUINDAPUNAN, PALO, LEYTE

CONST. OF FLOOD CONTROL ALONG SAMBULAWAN RIVER, BRGY. GUINDAPUNAN, PALO, LEYTE is a DPWH-tracked public work in Leyte 1st DEO, Region VIII. Reported contract value: ₱24,499,999.96. Status: Reported complete (DPWH). Contractor on record: COLLERA CONST. Figures trace to dpwh.

Leyte 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction Flood Control along Sambulawan River, Brgy. Guindapunan, Palo, Leyte
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-18-0003815

₱482,159.00 · FY2018

Released to Division of Southern (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱24,499,999.96

Progress

Reported complete (DPWH)

Start Date

February 6, 2018

Target End

September 3, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.