Roads17DM0004

REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM/ HIGHWAY DEVELOPMENT AND MANAGEMENT - 4 (HDM-4) ALONG P BURGOS-POTOTANIN JCT - K0153+(-808) - K0154+047 & K0164+688-K0165+000

REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM/ HIGHWAY DEVELOPMENT AND MANAGEMENT - 4 (HDM-4) ALONG P BURGOS-POTOTANIN JCT - K0153+(-808) - K0154+047 & K0164+688-K0165+000 is a DPWH-tracked public work in Quezon 3rd DEO, Region IV-A. Reported contract value: ₱28,951,160.00. Status: Reported complete (DPWH). Contractor on record: WAYCON BUILDERS AND CONST SUPPLY CORP FOR:WAYCON BUILDERS & CONST SUPPLY. Figures trace to dpwh.

Quezon 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Hingoso River, San Isidro Ibaba-San Vicente Section, General Luna, Quezon
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0021010

₱300,000,000.00 · FY2017

Released to Regional Field Unit - V (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Other projects by this contractor

No sat.

CLUSTER IV-ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-IV-I: DAANG MAHARLIKA (LZ) K0500+000-K0500+220, K0500+702-K0501+000, K0501+720-K0502+140, K0506+391.28-K0506+861, K0

Region V, Region V

2024₱408.7M
Past target date (DPWH On-Going)
No sat.

PREVENTIVE MAINTENANCE - PRIMARY ROADS DAANG MAHARLIKA (LZ) - K0096 + 586 - K0098 + 757, K0098 + 794 - K0099 + 082, K0100 + 440 - K0102 + 065, K0102 + 074 - K0102 + 450, K0102 + 475 - K0102 + 679

Region IV-A, Region IV-A

2024₱380.2M
Past target date (DPWH On-Going)
No sat.

LOCALLY FUNDED PROJECTS, CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-ROADS AND BRIDGES/WATER MANAGEMENT/WATER SUPPLY CONSTRUCTION OF BREAKWATER, BRGY. PUNTA, UNISAN, QUEZON

Region IV-A, Region IV-A

2017₱289.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS TAGKAWAYAN-LABO DIVERSION ROAD, (TAGKAWAYAN SECTION), QUEZON

Region IV-A, Region IV-A

2024₱280.4M
Past target date (DPWH On-Going)
No sat.

REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS DAANG MAHARLIKA (LZ)

Region IV-A, Region IV-A

2024₱262.2M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS-ALBAY WEST COAST RD-K0511+906-K0512+390, LIBON, ALBAY (3RD LEGISLATIVE DISTR

Region V, Region V

2024₱232.8M
Past target date (DPWH On-Going)
View all 72 projects →

4. Implementation

Contract Amount

₱28,951,160.00

Progress

Reported complete (DPWH)

Start Date

February 21, 2017

Target End

July 20, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.