Roads18IE0024

ASSET PRESERVATION-PREVENTIVE MAINTENANCE-TERTIARY ROADS, SAN ISIDRO-DAJA ROAD-S00078LT, K1018+(-1005)-K1018+(-469), K1018+(-450)-K1019+980, K1019+1001-K1020+000SAN ISIDRO, LEYTE

ASSET PRESERVATION-PREVENTIVE MAINTENANCE-TERTIARY ROADS, SAN ISIDRO-DAJA ROAD-S00078LT, K1018+(-1005)-K1018+(-469), K1018+(-450)-K1019+980, K1019+1001-K1020+000SAN ISIDRO, LEYTE is a DPWH-tracked public work in Leyte 3rd DEO, Region VIII. Reported contract value: ₱28,939,113.16. Status: Reported complete (DPWH). Contractor on record: YAKAL CONST. Figures trace to dpwh.

Leyte 3rd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱20,284,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Salog River, Leyte
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-18-0003815

₱482,159.00 · FY2018

Released to Division of Southern (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

59 projects · ₱4.1B total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - JCT. MILAGROS - BALENO - LAGTA RD. (S00016MT) - K0025+(-115) - K0030+140, MILAGROS, MASBATE

Masbate 2nd DEO, Region V

2022₱285.0M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - JCT. MILAGROS - BALENO - LAGTA RD. (S00016MT) - K0042+682 - K0045+725, MANDAON, MASBATE

Masbate 2nd DEO, Region V

2022₱172.7M
Past target date (DPWH On-Going)
No sat.

OO1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM (MFO-1)NATIONAL DEVELOPMENT-CONSTRUCTION OF MISSING LINKS/NEW ROADS, ASID-TIGBAO-BARA-MALBUG ROAD, INCLUDING ROW, MASBATE PROVINCE

Region V, Region V

2018₱172.6M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - JCT. TAWAD - BALUD RD. (S00023MT) - K0028+(-360) - K0028+944, K0029+910 - K0031+930, MILAGROS, MASBATE

Masbate 2nd DEO, Region V

2022₱158.2M
Past target date (DPWH On-Going)
No sat.

WIDENING ALONG BILIRAN CIR. ROAD, K1010+490-K1011+488; K1024+034-K1025+202; K1057+200-K1058+912; K1057+200-K1058+912; K1064+000-K1064+716; K1066+162-K1066+162-K1067+000; K1108+609, BILIRAN, NAVAL, KAWAYAN, CULABA & CABUCGAYAN, BILIRAN LONE DISTRICT ...,

Biliran DEO, Region VIII

2017₱156.2M
Reported complete (DPWH)
No sat.

ROAD WIDENING OF NAVAL - CAIBIRAN CROSS COUNTRY ROAD- K1027+890-K1028+210, K1028+268-K1028+770, K1033+738-K1033+980, K1033+1020-K1034+700, K1036+000-K1036+530, K1036+570-K1037+190, K1037+192-K1037+708, K1044+483.5-K1045+536, BILIRAN DISTRICT

Region VIII, Region VIII

2018₱140.1M
Past target date (DPWH On-Going)
View all 59 projects →

4. Implementation

Contract Amount

₱28,939,113.16

Progress

Reported complete (DPWH)

Start Date

February 7, 2018

Target End

June 21, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.