Flood Control and Drainage19DQ0038

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF REVETMENT AND OTHER IMPROVEMENTS ALONG METIZO RIVER,

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF REVETMENT AND OTHER IMPROVEMENTS ALONG METIZO RIVER, is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱46,312,437.93. Status: Reported complete (DPWH). Contractor on record: PRIME PACIFIC MARINE. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

22 projects · ₱936.5M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF NAVOTAS COASTAL DIKE, NAVOTAS CITY (STA. 0+508.50 - STA. 520.70 - STA. 1+453.60 - STA. 1+523, STA. 1+535.00 - STA. 1+540.00, STA. 1+595.70 - STA. 1+622.50, STA 3+021.40 - STA. 3+295.00)

Flood Control Management Cluster, Central Office

2019₱137.5M
Past target date (DPWH On-Going)
No sat.

CONTRUCTION OF REVETMENT AND IMPROVEMENTS ALONG BACOOR RIVER HABAY II PHASE I BACOOR CAVITE AND CONSTRUCTION OF REVETMENT AND OTHER IMPROVEMENTS ALONG BACOOR RIVER HABAY II PHASE II BACOOR CAVITE

Region IV-A, Region IV-A

2019₱78.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF REVETMENT AND OTHER IMPROVEMENTS ALONG CARMONA-BIÑAN RIV

Cavite 3rd DEO, Region IV-A

2021₱77.2M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF REVETMENT AND OTHER IMPROVEMENTS ALONG CARMONA-BIÑAN RIV

Cavite 3rd DEO, Region IV-A

2021₱77.2M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF REVETMENT ALONG SAN ISIDRO RIVER, PHASE 2, BARANGAY MADERAN, GENERAL MARIANO ALVAREZ, CAVITE

Cavite 3rd DEO, Region IV-A

2023₱67.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF REVETMENT AND OTHER IMPROVEMENTS ALONG METIZO RIVER, B

Cavite 3rd DEO, Region IV-A

2020₱50.9M
Reported complete (DPWH)
View all 22 projects →

4. Implementation

Contract Amount

₱46,312,437.93

Progress

Reported complete (DPWH)

Start Date

July 29, 2019

Target End

April 23, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.