Roads19KI0004

CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS SECONDARY ROAD, CALAMBA - BALIANGAO ROAD K1793+933 - K1794+115

CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS SECONDARY ROAD, CALAMBA - BALIANGAO ROAD K1793+933 - K1794+115 is a DPWH-tracked public work in Misamis Occidental 1st DEO, Region X. Reported contract value: ₱1,919,552.06. Status: Reported complete (DPWH). Contractor on record: GENETIAN BUILDERS AND ENT INC FORMERLY: GENETIAN BUILDERS. Figures trace to dpwh.

Misamis Occidental 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-LGRCB-19-0002308

₱200,000.00 · FY2019

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱1,919,552.06

Progress

Reported complete (DPWH)

Start Date

June 20, 2019

Target End

September 17, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.