Buildings and Facilities18DB0193

CONSTRUCTION AND COMPLETION OF SCHOOL BUILDING TWO (2) STOREY FOUR (4) CLASSROOM AT DONA MATILDE MES, LEMERY, BATANGAS

CONSTRUCTION AND COMPLETION OF SCHOOL BUILDING TWO (2) STOREY FOUR (4) CLASSROOM AT DONA MATILDE MES, LEMERY, BATANGAS is a DPWH-tracked public work in Batangas 1st DEO, Region IV-A. Reported contract value: ₱8,800,908.00. Status: Reported complete (DPWH). Contractor on record: JUBER CONST. Figures trace to dpwh.

Batangas 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Revetment @ Matingain 1 Creek, Brgy. Matingain 1, Lemery, Batangas
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-18-0016454

₱15,000,000.00 · FY2018

Released to Regional Office - IVA (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

57 projects · ₱206.0M total · 0 flags

4. Implementation

Contract Amount

₱8,800,908.00

Progress

Reported complete (DPWH)

Start Date

July 11, 2018

Target End

January 6, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.