Roads23IJ0045

CSSP: (RE-ADVERTISED) CONSTRUCTION OF ROAD PHASE 1, BRGY. CURRY - AGRUFACION TO BRGY. JOLACAO - CAMPERITO, STA. MARGARITA, SAMAR

CSSP: (RE-ADVERTISED) CONSTRUCTION OF ROAD PHASE 1, BRGY. CURRY - AGRUFACION TO BRGY. JOLACAO - CAMPERITO, STA. MARGARITA, SAMAR is a DPWH-tracked public work in Samar 1st DEO, Region VIII. Reported contract value: ₱48,510,414.87. Status: Reported complete (DPWH). Contractor on record: ETAN CONST. Figures trace to dpwh.

Samar 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project, Gandara, Samar
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Samar 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

138 projects · ₱4.2B total · 0 flags

4. Implementation

Contract Amount

₱48,510,414.87

Progress

Reported complete (DPWH)

Start Date

August 3, 2023

Target End

February 28, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.