Rehabilitation / Major Repair of Flood Control Structure24OF0003

Rehabilitation of Flood Control Structure at St. James, Barangay Nagkaisang Nayon, Quezon City

Rehabilitation of Flood Control Structure at St. James, Barangay Nagkaisang Nayon, Quezon City is a DPWH-tracked public work in QUEZON CITY (METROPOLITAN MANILA), QUEZON CITY, National Capital Region. Reported contract value: ₱29,399,739.03. Status: Reported complete (DPWH). Contractor on record: FRAMECON BUILDERS. Figures trace to sumbong.

QUEZON CITY (METROPOLITAN MANILA), QUEZON CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure at St. James, Barangay Nagkaisang Nayon, Quezon City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0003156

₱1,401,164.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0000560

₱173,180.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0000559

₱1,853,574.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0003157

₱123,131.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0008765

₱168,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0008750

₱1,815,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

24OF0003 – REHABILITATION OF FLOOD CONTROL STRUCTU

₱29,105,900.00 · FRAMECON BUILDERS

Contractor

B

495 projects · ₱7.8B total · 4 flags

4. Implementation

Contract Amount

₱29,399,739.03

Progress

Reported complete (DPWH)

Start Date

February 6, 2024

Target End

November 1, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.