Flood Control and Drainage24M00070

CONSTRUCTION OF FLOOD CONTROL DIKE ALONG KABACAN RIVER (PHASE III), BARANGAY ALEGRIA, STA.44+611.63-STA. 45+152, PRES. ROXAS, COTABATO

CONSTRUCTION OF FLOOD CONTROL DIKE ALONG KABACAN RIVER (PHASE III), BARANGAY ALEGRIA, STA.44+611.63-STA. 45+152, PRES. ROXAS, COTABATO is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱95,521,390.47. Status: Past target date (DPWH On-Going). Contractor on record: ILBI CONST SUPPLY. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

26 projects · ₱672.3M total · 0 flags

4. Implementation

Contract Amount

₱95,521,390.47

Progress

Past target date (DPWH On-Going)

Start Date

April 11, 2024

Target End

April 2, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.