Flood Control and Drainage20CD0011

CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BULO RIVER (KING KABAYO SECTION) PHASE VIII, SAN MIGUEL, BULACAN

CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BULO RIVER (KING KABAYO SECTION) PHASE VIII, SAN MIGUEL, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱29,948,763.36. Status: Reported complete (DPWH). Contractor on record: FLORDES CONST. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱47,336,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Bulo River (King Kabayo Section), Phase IX, San Miguel, Bulacan
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Bulacan 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

333 projects · ₱17.6B total · 0 flags

4. Implementation

Contract Amount

₱29,948,763.36

Progress

Reported complete (DPWH)

Start Date

February 17, 2020

Target End

July 24, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.