GAA 2025 SSP25FA0039

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) CONVERTIBLE TO EVACUATION CENTER AT SAN ISIDRO, STO. DOMINGO, ALBAY

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) CONVERTIBLE TO EVACUATION CENTER AT SAN ISIDRO, STO. DOMINGO, ALBAY is a DPWH-tracked public work in Albay 1st DEO, Region V. Reported contract value: ₱11,487,667.23. Status: Past target date (DPWH On-Going). Contractor on record: JORMAND CONST. Figures trace to dpwh.

Albay 1st DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Embankment Protection Works, Guinobat CIS, Tabaco City, Albay
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Albay 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱11,487,667.23

Progress

Past target date (DPWH On-Going)

Start Date

October 13, 2025

Target End

March 1, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.