Rehabilitation / Major Repair of Flood Control Structure22OD0214

Rehabilitation of Casili Creek from Samson Road to Estero de Maypajo, Barangays 34, 36 up to Barangay 75, Caloocan City

Rehabilitation of Casili Creek from Samson Road to Estero de Maypajo, Barangays 34, 36 up to Barangay 75, Caloocan City is a DPWH-tracked public work in CALOOCAN CITY (METROPOLITAN MANILA), CALOOCAN CITY, National Capital Region. Reported contract value: ₱28,813,987.65. Status: Reported complete (DPWH). Contractor on record: IM CONST CORP. Figures trace to sumbong.

CALOOCAN CITY (METROPOLITAN MANILA), CALOOCAN CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Wall along the Banks of Creeks, Brgy. 169, Caloocan City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002758

₱421,090,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001739

₱150,239,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003179

₱1,355,100,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003051

₱37,450,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001635

₱4,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001969

₱145,188,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

304 projects · ₱10.7B total · 6 flags

4. Implementation

Contract Amount

₱28,813,987.65

Progress

Reported complete (DPWH)

Start Date

March 22, 2022

Target End

January 15, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.