Roads21AD0015

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROAD ALONG TAGUDIN-CERVANTES ROAD-K0334+640-K0334+699, SUYO, ILOCOS SUR

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROAD ALONG TAGUDIN-CERVANTES ROAD-K0334+640-K0334+699, SUYO, ILOCOS SUR is a DPWH-tracked public work in Ilocos Sur 2nd DEO, Region I. Reported contract value: ₱41,159,543.80. Status: Reported complete (DPWH). Contractor on record: A I P CONST. Figures trace to dpwh.

Ilocos Sur 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Cabugao Flood Control, Barangay Cabugao, Suyo, Ilocos Sur
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Ilocos Sur 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

141 projects · ₱9.3B total · 1 flags

Other projects by this contractor

No sat.

CLUSTER: ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS MT. PROVINCE - CAGAYAN VIA TABUK - ENRILE R

Cordillera Administrative Region, Cordillera Administrative Region

2021₱289.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS / NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4B OF BLIS

Cordillera Administrative Region, Cordillera Administrative Region

2021₱284.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4A)

Cordillera Administrative Region, Cordillera Administrative Region

2020₱235.1M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - MT. PROVINCE - N VIZCAYA RD - K0363+(-785) - K0372+1019, K0372+1041 - K0375+000BONTOC, MT. PROVINCE

Cordillera Administrative Region, Cordillera Administrative Region

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4B OF BLISTT O

Cordillera Administrative Region, Cordillera Administrative Region

2022₱193.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - MT. PROVINCE - ILOCOS SUR VIA TUE RD, K0387+(-081) - K0388+189, K0388+227 - K0388+867, K0388+939 - K0388+1069

Cordillera Administrative Region, Cordillera Administrative Region

2024₱193.0M
Reported complete (100% progress, DPWH status On-Going)
View all 141 projects →

4. Implementation

Contract Amount

₱41,159,543.80

Progress

Reported complete (DPWH)

Start Date

July 19, 2021

Target End

March 15, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.