Buildings and Facilities17EB0147

CLUSTER 2017BEFF-09: CONSTRUCTION OF CLASSROOMS (BATCH 12):A) STA. ROSA ES, 1STY3CL, GRADE 1-10 CLB) GEN. E. AGUINALDO ES, 1STY2CLC) MALISBONG ES, 1STY2CLD) SAN NICOLAS ES, 1STY2CLE) TUBAN ES, 1STY2CL

CLUSTER 2017BEFF-09: CONSTRUCTION OF CLASSROOMS (BATCH 12):A) STA. ROSA ES, 1STY3CL, GRADE 1-10 CLB) GEN. E. AGUINALDO ES, 1STY2CLC) MALISBONG ES, 1STY2CLD) SAN NICOLAS ES, 1STY2CLE) TUBAN ES, 1STY2CL is a DPWH-tracked public work in Mindoro Occidental DEO, Region IV-B. Reported contract value: ₱12,559,467.47. Status: Reported complete (DPWH). Contractor on record: JEENE-SON CONST. Figures trace to dpwh.

Mindoro Occidental DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Magbando Flood Control, San Jose Occidental Mindoro
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-17-0000040

₱213,291.00 · FY2017

Released to 0008 - Regional Office VIII Ter Oli (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

32 projects · ₱202.4M total · 0 flags

4. Implementation

Contract Amount

₱12,559,467.47

Progress

Reported complete (DPWH)

Start Date

February 5, 2018

Target End

June 22, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.