Roads24DD0280

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CONSTRUCTION OF LUMBANG-INOSLOBAN BYPASS ROAD (PACKAGE J), LIPA CITY, BATANGAS

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CONSTRUCTION OF LUMBANG-INOSLOBAN BYPASS ROAD (PACKAGE J), LIPA CITY, BATANGAS is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱140,552,168.57. Status: Past target date (DPWH On-Going). Contractor on record: NEWINGTON BUILDERS INC FOR: E GARDIOLA CONSTRUC. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bawi and Banaba Creek, Padre Garcia, Batangas
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Batangas 4th DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

189 projects · ₱20.4B total · 0 flags

4. Implementation

Contract Amount

₱140,552,168.57

Progress

Past target date (DPWH On-Going)

Start Date

March 7, 2025

Target End

December 31, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.