Roads17JD0023

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) PIÑAN-MUTIA ROAD K1833+940-K1834+068,K1834+320-K1843+700,K1838+340-K1838+601 & CHAINAGE 548- CHAINAGE 969

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) PIÑAN-MUTIA ROAD K1833+940-K1834+068,K1834+320-K1843+700,K1838+340-K1838+601 & CHAINAGE 548- CHAINAGE 969 is a DPWH-tracked public work in Zamboanga del Norte 1st DEO, Region IX. Reported contract value: ₱42,097,618.10. Status: Reported complete (DPWH). Contractor on record: RUDHIL CONST. Figures trace to dpwh.

Zamboanga del Norte 1st DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Dipolog River Flood Control Development Project, Barangay Turno and Barra, Dipolog City, Zamboanga del Norte
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-17-0019250

₱-227,620.00 · FY2017

Released to Pampanga 1st District Engineering Of (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

1,028 projects · ₱22.5B total · 0 flags

4. Implementation

Contract Amount

₱42,097,618.10

Progress

Reported complete (DPWH)

Start Date

March 13, 2017

Target End

April 12, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.