Water Provision and Storage23K00228

CONSTRUCTION OF SOLAR WATER SYSTEM, MUNICIPALITY OF BUBONG, LANAO DEL SUR

CONSTRUCTION OF SOLAR WATER SYSTEM, MUNICIPALITY OF BUBONG, LANAO DEL SUR is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱8,892,439.94. Status: Reported complete (DPWH). Contractor on record: N B SALBO CONST. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱8,892,439.94

Progress

Reported complete (DPWH)

Start Date

December 18, 2023

Target End

May 15, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.