Buildings and Facilities21OF0230

CONSTRUCTION/ IMPROVEMENT OF MULTI-PURPOSE BUILDING, PROJECT 6, QUEZON CITY

CONSTRUCTION/ IMPROVEMENT OF MULTI-PURPOSE BUILDING, PROJECT 6, QUEZON CITY is a DPWH-tracked public work in Quezon City 1st DEO, National Capital Region. Reported contract value: ₱9,583,006.40. Status: Reported complete (DPWH). Contractor on record: PERRC INC FORMERLY: P E R R C CONST. Figures trace to dpwh.

Quezon City 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱6,996,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Improvement of Flood Control Structure at Matalahib Creek, Quezon City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Quezon City 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

43 projects · ₱2.5B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE & SPL. SUPP. PROG.-SUSTAINABLE INFRASTRUCTURE PROJS. ALLEVIATING GAPS (SIPAG)-INTERJURISDICTIONAL RDS. &/OR BRS. (OR,RDS. THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), CONST. OF BYPASS RD. (PHASE 8) AT DONA REMEDIOS TRINIDAD TO SAN JOSE DEL MONTE

Region III, Region III

2024₱283.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE & SPL. SUPP. PROG.-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-INTERJURISDICTIONAL RDS. &/OR BRS. (OR,RDS. THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) CONST. OF BYPASS RD. AT DONA REMEDIOS TRINIDAD TO SAN JOSE DEL MONTE CITY (PHASE 9), B

Region III, Region III

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM-LOCAL ROADS & BRIDGES-LOCAL ROADS-CONSTRUCTION OF BYPASS ROAD AT DONA REMEDIOS TRINIDAD TO SAN JOSE DEL MONTE, PROVINCE OF BULACAN

Region III, Region III

2021₱188.0M
Reported complete (DPWH)
No sat.

WIDENING OF PUERTO PRINCESA SOUTH ROAD FROM TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE STRUCTURES & OTHER ANCILLARY WORKS, KO139+800-KO141+891

Region IV-B, Region IV-B

2018₱144.8M
Reported complete (DPWH)
No sat.

WIDENING OF PUERTO PRINCESA SOUTH ROAD FROM TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE & OTHER ANCILLARY WORKS, KO226+400-KO226+537; KO226+562-KO228+954, BATARAZA, PALAWAN

Region IV-B, Region IV-B

2018₱144.8M
Reported complete (DPWH)
No sat.

WIDENING OF PUERTO PRINCESA SOUTH ROAD FROM TWO (2) TO SIX (6) LANES INCL DRAINAGE STRUCTURES AND OTHER ANCILLARY WORKS K0175+627-K0176+185; K0176+194-K0177+880, BROOKE'S POINT, PALAWAN

Region IV-B, Region IV-B

2018₱135.1M
Reported complete (DPWH)
View all 43 projects →

4. Implementation

Contract Amount

₱9,583,006.40

Progress

Reported complete (DPWH)

Start Date

December 7, 2021

Target End

July 4, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.