Buildings and Facilities24IA0063

CONSTRUCTION OF TWO-STOREY OFFICE BUILDING, DPWH BILIRAN DEO, DPWH BUREAU OF EQUIPMENT, 8TH RES, BARANGAY LARRAZABAL, NAVAL, BILIRAN

CONSTRUCTION OF TWO-STOREY OFFICE BUILDING, DPWH BILIRAN DEO, DPWH BUREAU OF EQUIPMENT, 8TH RES, BARANGAY LARRAZABAL, NAVAL, BILIRAN is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱48,540,810.60. Status: Past target date (DPWH On-Going). Contractor on record: AQUALINE CONST CORP FORMERLY: AQUALINE CONST. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Agpangi, Naval, Biliran
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Biliran DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

245 projects · ₱18.1B total · 0 flags

4. Implementation

Contract Amount

₱48,540,810.60

Progress

Past target date (DPWH On-Going)

Start Date

February 19, 2024

Target End

April 3, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.