CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), POBLACION, LAKE SEBU, SOUTH COTABATO is a DPWH-tracked public work in South Cotabato 2nd DEO, Region XII. Reported contract value: ₱1,760,452.15. Status: Reported complete (DPWH). Contractor on record: BARRIST BUILDERS AND CONST SUPPLY 39785. Figures trace to dpwh.

South Cotabato 2nd DEO, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,760,452.15

Progress

Reported complete (DPWH)

Start Date

October 16, 2020

Target End

January 18, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.