Buildings and Facilities18MH0110

CONSTRUCTION OF TWO (2) STOREY - TWO (2) LABORATORY (ICT) AT E. ARCAÑO MEMORIAL NATIONAL HIGH SCHOOL LEBAK, SULTAN KUDARAT

CONSTRUCTION OF TWO (2) STOREY - TWO (2) LABORATORY (ICT) AT E. ARCAÑO MEMORIAL NATIONAL HIGH SCHOOL LEBAK, SULTAN KUDARAT is a DPWH-tracked public work in Sultan Kudarat 2nd DEO, Region XII. Reported contract value: ₱9,997,900.35. Status: Reported complete (DPWH). Contractor on record: BARRIST BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Sultan Kudarat 2nd DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Seawall Protection, Brgy Baranayan, Palimbang, Sultan Kudarat
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-18-0004078

₱54,219.00 · FY2018

Released to Caduha-an National High re School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,997,900.35

Progress

Reported complete (DPWH)

Start Date

August 2, 2018

Target End

November 30, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.