Buildings and Facilities17BD0092

CONSTRUCTION OF ONE (1) TWO STOREY MULTI-PURPOSE BUILDING (PHASE I), BRGY. UNAG, AMULUNG, CAGAYAN

CONSTRUCTION OF ONE (1) TWO STOREY MULTI-PURPOSE BUILDING (PHASE I), BRGY. UNAG, AMULUNG, CAGAYAN is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱954,195.34. Status: Reported complete (DPWH). Contractor on record: JOHN 6:51 BUILDERS. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System, Sta. 0+240 – Sta. 0+540, Brgy. Fugu, Tuao, Cagayan
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0025300

₱5,300,000.00 · FY2017

Released to Regional Office - Proper (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Possible match · 80%

Construction of Small Water Impounding Project

₱989,861.57 · JOHN 6:51 BUILDERS

Contractor

90 projects · ₱398.0M total · 0 flags

4. Implementation

Contract Amount

₱954,195.34

Progress

Reported complete (DPWH)

Start Date

June 8, 2017

Target End

August 6, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.