Roads22FA0092

REHAB. OF ROAD WITH SLIP, SLOPE COLLAPSE AND LANDSLIDE AT SITIO INABUYAN, ALIMSOG, STO. DOMINGO, ALBAY

REHAB. OF ROAD WITH SLIP, SLOPE COLLAPSE AND LANDSLIDE AT SITIO INABUYAN, ALIMSOG, STO. DOMINGO, ALBAY is a DPWH-tracked public work in Albay 1st DEO, Region V. Reported contract value: ₱96,500,000.00. Status: Reported complete (DPWH). Contractor on record: CENTERWAYS CONST AND DEVELOPMENT INC. Figures trace to dpwh.

Albay 1st DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Basud River Flood Control System (Upstream), Sto. Domingo, Albay
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Albay 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

309 projects · ₱22.7B total · 8 flags

4. Implementation

Contract Amount

₱96,500,000.00

Progress

Reported complete (DPWH)

Start Date

December 27, 2022

Target End

October 14, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.