GAA 2025 OO-225BA0040

OO2: PROTECT LIVES AND PROPERTIES AGAINST: MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF FLOOD CONTROL STRUCTURE, DICHOD SECTION, BARANGAY KAYUGANAN, UYUGAN, BATANES

OO2: PROTECT LIVES AND PROPERTIES AGAINST: MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF FLOOD CONTROL STRUCTURE, DICHOD SECTION, BARANGAY KAYUGANAN, UYUGAN, BATANES is a DPWH-tracked public work in Batanes DEO, Region II. Reported contract value: ₱19,579,315.04. Status: Past target date (DPWH On-Going). Contractor on record: J F GABOTERO INC. Figures trace to dpwh.

Batanes DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Dichod Section, Barangay Kayuganan, Uyugan, Batanes
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Batanes DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

29 projects · ₱449.1M total · 1 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINSTMAJOR FLOODS- FLOOD MANAGEMENT PROGRAM:CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS:CONSTRUCTION OF GUARDWALL ALONG AIRPORT-MAUYEN PORT ROAD, ITBAYAT, BATANES

Batanes DEO, Region II

2025₱49.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS; FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS -CONSTRUCTION OF SEA WALL AT IVANA SHELTER PORT, IVANA, BATANES

Batanes DEO, Region II

2024₱39.1M
Past target date (DPWH On-Going)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM; CONSTRUCTION OF GUARDWALL ALONG SAN VICENTE- SAVIDUG- CHAVAYAN- SUMNANGA- NAKANMUAN RD, SABTANG, BATANES

Batanes DEO, Region II

2024₱35.3M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM:ASSET PRESERVATION PROGRAM:CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-TERTIARY ROADS:MAYAN-MAUYEN PORT ROAD-K0000+040-K0000+145,K0000+225-K0000+516

Batanes DEO, Region II

2025₱29.4M
Past target date (DPWH On-Going)
No sat.

Construction of Guardwall (along Basco-Mahatao-Ivana-Uyugan-Imnajbu Road), Basco, Batanes

BASCO (CAPITAL) (BATANES), BATANES, Region II

2023₱24.1M
Reported complete (DPWH)
No sat.

Construction of Nakanmuan Seawall, Barangay Nakanmuan, Sabtang, Batanes

SABTANG (BATANES), BATANES, Region II

2023₱21.2M
Reported complete (DPWH)
View all 29 projects →

4. Implementation

Contract Amount

₱19,579,315.04

Progress

Past target date (DPWH On-Going)

Start Date

March 31, 2025

Target End

January 31, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.