Flood Control and Drainage19LE0078

CONSTRUCTION OF CONCRETE REVETMENT (RC-CUT OFF WALL), PONGPONG FLOOD CONTROL, STA. MARIA, DAVAO OCCIDENTAL STA.0+540 - STA.0+000 (LEFT BANK), STA.0+660 - STA.0+000 (RIGHT BANK)

CONSTRUCTION OF CONCRETE REVETMENT (RC-CUT OFF WALL), PONGPONG FLOOD CONTROL, STA. MARIA, DAVAO OCCIDENTAL STA.0+540 - STA.0+000 (LEFT BANK), STA.0+660 - STA.0+000 (RIGHT BANK) is a DPWH-tracked public work in Davao Occidental DEO, Region XI. Reported contract value: ₱57,850,196.97. Status: Reported complete (DPWH). Contractor on record: FFJJ CONST. Figures trace to dpwh.

Davao Occidental DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-19-0003090

₱180,662.00 · FY2019

Released to Regional Field Unit - II (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

788 projects · ₱27.5B total · 2 flags

4. Implementation

Contract Amount

₱57,850,196.97

Progress

Reported complete (DPWH)

Start Date

June 26, 2019

Target End

January 27, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.