Construction of Revetment22LA0045

Construction of Revetment along Manat River (Up- stream and Down Stream) leading to Agusan River at Prk1C, 1B, 1A, 7, 8 and Manat Bridge, Sta. 15+780 - Sta. 16+170 (LS), Brgy. Poblacion, Montevista, Davao de Oro

Construction of Revetment along Manat River (Up- stream and Down Stream) leading to Agusan River at Prk1C, 1B, 1A, 7, 8 and Manat Bridge, Sta. 15+780 - Sta. 16+170 (LS), Brgy. Poblacion, Montevista, Davao de Oro is a DPWH-tracked public work in MONTEVISTA (DAVAO DE ORO), DAVAO DE ORO, Region XI. Reported contract value: ₱48,999,898.13. Status: Reported complete (DPWH). Contractor on record: AB APONESTO CONST PARTS AND SUPPLY INC. Figures trace to sumbong.

MONTEVISTA (DAVAO DE ORO), DAVAO DE ORO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Batutu River leading to Manat River, Barangay Banag-Banag, Montevista, Davao de Oro
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003152

₱756,564,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002642

₱535,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002791

₱62,400,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002783

₱45,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0006775

₱37,000,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱48,999,898.13

Progress

Reported complete (DPWH)

Start Date

February 15, 2022

Target End

November 5, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.