CONSTRUCTION OF LOPEZ VIADUCT ALONG DAANG MAHARLIKA, LOPEZ, QUEZON

CONSTRUCTION OF LOPEZ VIADUCT ALONG DAANG MAHARLIKA, LOPEZ, QUEZON is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱49,371,199.60. Status: Past target date (DPWH On-Going). Contractor on record: M G LUALHATI CONST CORP 35373. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱49,371,199.60

Progress

Past target date (DPWH On-Going)

Start Date

September 26, 2023

Target End

May 22, 2024

5. Audit