Bridges24D00013

CONSTRUCTION OF MISSING LINKS / NEW ROADSMSR JCT CANDA - HONDAGUA ROMA POINT ROAD, PACKAGE A, QUEZON

CONSTRUCTION OF MISSING LINKS / NEW ROADSMSR JCT CANDA - HONDAGUA ROMA POINT ROAD, PACKAGE A, QUEZON is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱380,928,394.60. Status: Past target date (DPWH On-Going). Contractor on record: M G LUALHATI CONST CORP. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱380,928,394.60

Progress

Past target date (DPWH On-Going)

Start Date

February 28, 2024

Target End

December 23, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.