Flood Control and Drainage24IC0080

CONSTRUCTION OF TIBAK FLOOD CONTROL STRUCTURE AND DRAINAGE SYSTEM, TIBAK RIVER, STA. FE, LEYTE

CONSTRUCTION OF TIBAK FLOOD CONTROL STRUCTURE AND DRAINAGE SYSTEM, TIBAK RIVER, STA. FE, LEYTE is a DPWH-tracked public work in Leyte 1st DEO, Region VIII. Reported contract value: ₱125,417,644.36. Status: Past target date (DPWH On-Going). Contractor on record: EZJONES CONST INC. Figures trace to dpwh.

Leyte 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure ( Drainage Canal ) , Zone 2, Barangay Capangihan, Tolosa, Leyte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Leyte 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

287 projects · ₱36.2B total · 7 flags

Other projects by this contractor

View all 287 projects →

4. Implementation

Contract Amount

₱125,417,644.36

Progress

Past target date (DPWH On-Going)

Start Date

May 2, 2024

Target End

May 20, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.