Roads19K00413

CONCRETING OF BRGY. BONGALO-BRGY. UPPER ITIL FMR, BRGY. BONGALO AND BRGY. UPPER ITIL, BALABAGAN, LANAO DEL SUR

CONCRETING OF BRGY. BONGALO-BRGY. UPPER ITIL FMR, BRGY. BONGALO AND BRGY. UPPER ITIL, BALABAGAN, LANAO DEL SUR is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱9,651,389.21. Status: Reported complete (DPWH). Contractor on record: GOLDEN BUILDERS. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱9,651,389.21

Progress

Reported complete (DPWH)

Start Date

December 17, 2019

Target End

April 1, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.