Construction of Flood Mitigation Structure24CG0012

Construction of Eroded Bank along Pampanga River, Barangay Cansinala, Apalit, Pampanga

Construction of Eroded Bank along Pampanga River, Barangay Cansinala, Apalit, Pampanga is a DPWH-tracked public work in APALIT (PAMPANGA), PAMPANGA, Region III. Reported contract value: ₱73,322,904.70. Status: Reported complete (DPWH). Contractor on record: ANGEL BUILDERS & CONST SUPPLY / FRAMECON BUILDERS. Figures trace to sumbong.

APALIT (PAMPANGA), PAMPANGA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Pampanga River, Apalit, Pampanga
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0018103

₱25,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008249

₱1,906,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0005754

₱994,559.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0002412

₱426,959.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008250

₱176,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱73.3M total · 0 flags

4. Implementation

Contract Amount

₱73,322,904.70

Progress

Reported complete (DPWH)

Start Date

May 29, 2024

Target End

January 8, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.