Buildings and Facilities20MC0057

CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING, CONCEPCION, MAKILALA, NORTH COTABATO

CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING, CONCEPCION, MAKILALA, NORTH COTABATO is a DPWH-tracked public work in Cotabato 2nd DEO, Region XII. Reported contract value: ₱9,900,000.00. Status: Reported complete (DPWH). Contractor on record: GNTS CO OPERATING UNDER THE NAME OF GNTS BUILDERS. Figures trace to dpwh.

Cotabato 2nd DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱26,990,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Nicaan Flood Control Subsidiary of Libungan River, Libungan, Cotabato
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Cotabato 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,900,000.00

Progress

Reported complete (DPWH)

Start Date

February 28, 2020

Target End

August 10, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.