Bridges25D00062

WIDENING OF PERMANENT BRIDGES INALAKANAN BR. (B02590LZ) ALONG MAHARLIKA HIGHWAY

WIDENING OF PERMANENT BRIDGES INALAKANAN BR. (B02590LZ) ALONG MAHARLIKA HIGHWAY is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱18,667,463.91. Status: Past target date (DPWH On-Going). Contractor on record: M G LUALHATI CONST CORP 35373. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱18,667,463.91

Progress

Past target date (DPWH On-Going)

Start Date

March 6, 2025

Target End

October 1, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.