Roads15K00357

CONST. OF CDO DIVERSION RD(JCT BALUBAL),SH PUEBLO DE ORO,CDO OLD-AIRPORT DIVERSION RD(PUEBLO DE ORO/

CONST. OF CDO DIVERSION RD(JCT BALUBAL),SH PUEBLO DE ORO,CDO OLD-AIRPORT DIVERSION RD(PUEBLO DE ORO/ is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱132,887,383.11. Status: Reported complete (DPWH). Contractor on record: VEN RAY CONST CORP. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱132,887,383.11

Progress

Reported complete (DPWH)

Start Date

March 7, 2016

Target End

December 16, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.