Bridges25NF0065

RETROFITTING / STRENGTHENING OF PERMANENT BRIDGES SAN ISIDRO BRIDGE (B00016SG) ALONG JCT DEL CARMEN - STA. MONICA - SN ISIDRO RD

RETROFITTING / STRENGTHENING OF PERMANENT BRIDGES SAN ISIDRO BRIDGE (B00016SG) ALONG JCT DEL CARMEN - STA. MONICA - SN ISIDRO RD is a DPWH-tracked public work in Surigao del Norte 1st DEO, Region XIII. Reported contract value: ₱2,839,999.99. Status: Reported complete (DPWH). Contractor on record: BOOMETRIX DEVELOPMENT CORP. Figures trace to dpwh.

Surigao del Norte 1st DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure Purok 2, Brgy. Urbiztondo, Claver, Surigao del Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Surigao del Norte 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,839,999.99

Progress

Reported complete (DPWH)

Start Date

March 28, 2025

Target End

June 29, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.