Roads23PE0010

REHABILITATION OF PAVED ROAD - MARCOS HI-WAY (S00395LZ) - K0264+000 - K0264+460, K0266+000 - K0266+709, K0267+165 - K0267+325, TUBA, BENGUET

REHABILITATION OF PAVED ROAD - MARCOS HI-WAY (S00395LZ) - K0264+000 - K0264+460, K0266+000 - K0266+709, K0267+165 - K0267+325, TUBA, BENGUET is a DPWH-tracked public work in Benguet 1st DEO, Cordillera Administrative Region. Reported contract value: ₱55,569,923.20. Status: Reported complete (DPWH). Contractor on record: CLIFF CONST. Figures trace to dpwh.

Benguet 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱55,569,923.20

Progress

Reported complete (DPWH)

Start Date

February 27, 2023

Target End

December 4, 2023

5. Audit