Buildings and Facilities18OE0208

LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM-BUILDING AND OTHER STRUCTURES-MULTI-PURPOSE/FACILITIES-CONSTRUCTION AND REHABILITATION OF MULTI-PURPOSE BUILDING COVERED COURT, BARANGAY 118, MANILA

LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM-BUILDING AND OTHER STRUCTURES-MULTI-PURPOSE/FACILITIES-CONSTRUCTION AND REHABILITATION OF MULTI-PURPOSE BUILDING COVERED COURT, BARANGAY 118, MANILA is a DPWH-tracked public work in North Manila DEO, National Capital Region. Reported contract value: ₱4,794,008.09. Status: Reported complete (DPWH). Contractor on record: GUILLAND CONST. Figures trace to dpwh.

North Manila DEO, National Capital Region
Region: National Capital Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Bank Improvement (Steel Sheet Pile) and Rehabilitation of Tapping, Estero de Sampaloc, Sta. 0 + 455.95 to Sta. 0 + 525.75, Manila City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-18-0033895

₱0.00 · FY2018

Released to Dacap Norte National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,794,008.09

Progress

Reported complete (DPWH)

Start Date

July 30, 2018

Target End

November 26, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.