Construction of Flood Mitigation Structure24A00453

Construction of Flood Control Riverbank Structure along Aloragat and Allied Rivers, Package 2, Binalonan -Laoac, Pangasinan

Construction of Flood Control Riverbank Structure along Aloragat and Allied Rivers, Package 2, Binalonan -Laoac, Pangasinan is a DPWH-tracked public work in BINALONAN (PANGASINAN), PANGASINAN, Region I. Reported contract value: ₱48,249,942.73. Status: Reported complete (DPWH). Contractor on record: SILVERWOLVES CONST CORP. Figures trace to sumbong.

BINALONAN (PANGASINAN), PANGASINAN, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Tagamusing and Allied River, Binalonan, Pangasinan ( Package 1 )
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0007434

₱1,946,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0003000

₱441,770.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0007435

₱180,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0001275

₱159,815.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

179 projects · ₱19.9B total · 9 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF REVETMENT AND OTHER IMPROVEMENTS ALONG BALUCTOT RIVER, EAST SIDE, BRGY. SALAWAG, DASMARIÑAS, CAVITE

Region IV-A, Region IV-A

2024₱241.4M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF REVETMENT AND OTHER IMPROVEMENTS ALONG BALUCTOT RIVER, EAST SIDE, BRGY. PALIPARAN III, DASMARIÑAS, CAVITE (PHASE I)

Region IV-A, Region IV-A

2024₱241.4M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BENGUET NUEVA VIZCAYA RD, K0283+368 - K0283+475

Cordillera Administrative Region, Cordillera Administrative Region

2023₱241.3M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BENGUET NUEVA VIZCAYA RD, K0283+475 - K0283+575

Cordillera Administrative Region, Cordillera Administrative Region

2023₱241.3M
Reported complete (DPWH)
No sat.

SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF ROAD SAFETY DEVICES ALONG BAUANG-BAGUIO CITY ROAD, K0261+100 - K0261+300, K0262+300 - K0262+400, K0262+900 - K0263+100, K0263+500 - K0263+900, K0269+600 - K0269+750,

Region I, Region I

2023₱241.2M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG PAGBAHAN RIVER, PHASE 1, BRGY. SAN VICENTE, SANTA CRUZ, OC

Region IV-B, Region IV-B

2024₱241.2M
Reported complete (DPWH)
View all 179 projects →

4. Implementation

Contract Amount

₱48,249,942.73

Progress

Reported complete (DPWH)

Start Date

May 3, 2024

Target End

January 12, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.