Flood Control and Drainage23G00052

REHABILITATION OF UPPER INGORE CREEK, ILOILO CITY

REHABILITATION OF UPPER INGORE CREEK, ILOILO CITY is a DPWH-tracked public work in Region VI, Region VI. Reported contract value: ₱101,146,729.66. Status: Reported complete (DPWH). Contractor on record: A D PENDON CONST. Figures trace to dpwh.

Region VI, Region VI
Region: Region VI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱101,146,729.66

Progress

Reported complete (DPWH)

Start Date

February 7, 2023

Target End

November 8, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.