Buildings and Facilities23I00154

CONSTRUCTION OF STAFF HOUSE DPWH SOUTHERN LEYTE, 2ND DEO, SOGOD, SOUTHERN LEYTE

CONSTRUCTION OF STAFF HOUSE DPWH SOUTHERN LEYTE, 2ND DEO, SOGOD, SOUTHERN LEYTE is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱14,445,941.32. Status: Reported complete (DPWH). Contractor on record: BUILD SMART CONST AND DEVELOPMENT CORP 52028. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 52028

32 projects · ₱200.1M total · 0 flags

Other projects by this contractor

No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SHORELINE PROTECTION, BARANGAY TAMPOONG, SOGOD, SOUTHERN LEYTE

Southern Leyte 2nd DEO, Region VIII

2025₱24.4M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM (LP) - NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES - CONSTRUCTION OF DPWH MULTI-PURPOSE BUILDING (PHASE 1), SOGOD, SOUTHERN LEYTE

Southern Leyte 2nd DEO, Region VIII

2025₱19.3M
Past target date (DPWH On-Going)
No sat.

CLUSTER 23: 1. BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY BONGAWISAN, SAN FRANCISCO, SOUTHERN LEYTE; AND OTHER FOUR (4) PROJECTS

Region VIII, Region VIII

2023₱13.8M
Reported complete (DPWH)
No sat.

CONCRETING OF BRGY. CARNAGA TO BRGY. MANLICO FMR, BRGY. CARNAGA AND BRGY. MANLICO, SAINT BERNARD, SOUTHERN LEYTE

Region VIII, Region VIII

2023₱11.9M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM (LP) - NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES - CONSTRUCTION OF DPWH QAS BUILDING (PHASE 2), SOGOD, SOUTHERN LEYTE

Southern Leyte 2nd DEO, Region VIII

2025₱11.6M
Past target date (DPWH On-Going)
No sat.

BUILDINGS AND OTHER STRUCTURES-MULTIPURPOSE/FACILITIES - NATIONAL BUILDING PROGRAM - CONSTRUCTION OF QAS BUILDING, DPWH SOUTHERN LEYTE 2ND DEO, SOGOD, SOUTHERN LEYTE

Region VIII, Region VIII

2023₱11.6M
Reported complete (DPWH)
View all 32 projects →

4. Implementation

Contract Amount

₱14,445,941.32

Progress

Reported complete (DPWH)

Start Date

October 16, 2023

Target End

April 12, 2024